On site
Vivienne Residences on site: the build in photographs
Dated photographs of the building going up in Labone through 2026.

3 August 2026
Upper floors going up. The tower crane is in place and a concrete pump is on site.



29 May 2026
The concrete frame and the tower crane, seen from the ground.

27 March 2026
A concrete pour on a slab, and the lower floors from the air.



Construction started in Q4 2024 and completion is planned for Q3 2027. See Vivienne Residences.